Meeting Notes: August 5 2008 - Gallery Codex
Meeting Notes: August 5 2008
From Gallery Codex
Present
- ckdake (notes)
- joan
- Tim_j
- johndbritton
- schultmc
- bharat
- jozefs
- phinze
- jhilden
- valiant
- ymhee_bcex
- Joe7
Project Tasks
Gallery 1
- 1.5.8 and 1.6-RC1 are out.
- ~2 weeks of baking before RC2, then 4 weeks for final perhaps
Summer of Code
- firm deadline for all code is aug 18 (noon PDT). this monday (aug 11) is suggested pencils down date
- phinze and johndbritton both need reviews
- phinze finishes implementation work in 24 hours -> then needs more reviews (reviews been ongoing since 50% through summer). beta should be announced within a few days
- johndbritton status in -devel
Summer of Usability
- no big updates from jhilden
- continues to wait on feedback :(
- jhilden is moving back to the states on friday which is taking time this week and next
GCon
- Bharat is going to send out reimbursements for all submitted expenses soon. needs addresses first.
- Tim_j is going to make sure spreadsheet is accurate
Gallery 2.3
- 2.3-RC1 out the door, getting feedback, lots of small bugs
- lots of progress in the last week on blockers, fixing some bugs
- updated blockers left: http://codex.galleryproject.org/Gallery2:2.3_Release_Blockers
- bharat reminds us that RC should be best shot at final product
- jozefs spending next few days on sr translation, then will be available for bug fixing
- everyone else will continue fixing things
- RC2 maybe in 2-3 weeks
Gallery Competition
- Alec isn't here, will send update to -devel
Action Items For Next Week
(bold ones are overdue)
- ckdake
- continue to harass bharat about G1 reviews, G2 reviews, SoC
- harass people about reviews for SoC
- schultmc
- update us on corporation status "Real Soon Now"
- backport fixes and ask for code reviews or contact the security team to see if 2.2.5 can go in
- alindeman
- review 341: ffmpeg
- ping h0bbel to do something about paid support by next meeting
- beckett
- look through integrations page on codex and update (remove obsoletes)
Not at Meeting
- h0bbel
- finish putting together MS testing plan
- add more to test matrix for other platforms
- bharat
- send email about whats next for Gallery
Completed Action items from last week